Installing Electric
|
|
[lesson title] |
| The ground-cover requirements for underground conductors or conduit vary according to the site. In nontraffic areas, SE cable should be buried at least 18 inches and covered with a 2-inch-thick concrete pad (Figure 2-1). If rigid or intermediate conduit is installed, the depth can be reduced to 6 inches.
When SE cable is subject to vehicle traffic, at least 24-inces of ground cover is required (Figure2-2). The 24-inch-depth requirement will allow the service to withstand the weight of vehicles passing over it. The depth requirement is the same when conduit is used.
SE cable buried in solid-rock areas can be installed down to the surface of the rock if the cable is covered with at least 2 inches of concrete that extends to the rock surface (Figure 2-3). The same requirement exists for conduit.
Conductors coming out of the ground should be protected by enclosures, raceways, or conduit from below grade to 8 feet above the ground (Figure 2-4).
When backfilling a trench where there are cables or conductors, do not backfill with-
Placement of SEs. Underground services can be installed using either underground service entrance (USE) cable, direct-burial conductors, or conduit (Figure 2-5). Conductors should not be spliced unless they are placed in a properly installed splice box.
When direct-burial conductors or USE cables are above grade they must be protected in the plastic or metallic conduit at both ends (Figure 2-6).
The installation of a USE to the power panel varies according to the site and the equipment. (Figure 2-7) shows a typical setup that is subject to change to fit the installation.
|
| Content provider: U.S. Army, David L. Heiserman Publisher: SweetHaven Publishing Services |
Copyright © 2005, SweetHaven
Publishing Services |
Revised: April 19, 2005